IMPORTANT: Before and after replacement, execute the "Repair" service
function with the
BMW diagnosis system.
Recycling:
Catch and dispose of escaping transmission fluid. Observe country-specific
waste-disposal regulations.
IMPORTANT: After completing work, check transmission oil level and top
up if necessary.
Release filler plug (1).
Check oil level.
Tightening torque 27 00 11AZ, see TRANSFER BOX IN GENERAL.
Pour in transmission oil up to lower edge of opening for filler plug (1).
Use only the approved transmission oil.
Failure to comply with this requirement will result in serious damage to the
transfer box!
Fig. 7: Identifying Oil Filler Plug
Necessary preliminary tasks:
Modify following parts:
- Covers and protective caps
- Drive shaft transportation lock
- Vent hose of transfer box
REPLACING OUTPUT FLANGE ON TRANSFER BOX AT REAR (ATC 700)
IMPORTANT: After completing work, check gear oil level. See TRANSFER
BOX IN
GENERAL and top up if necessary.
Use only the approved gear oil in this transfer box.
NOTE:
- Operations for removing output flange are identical to replacing
radial
shaft seal.
Installation:
- Thickness of new shim must be determined before output flange is
installed
Determine and note down measurement A of output flange (previous and new).
Fig. 8: Checking Measurement A
Determine and note down measurement B of output flange (previous and new).
Fig. 9: Checking Measurement B
Determine measurement C, thickness of shim.
Fig. 10: Checking Measurement C
Installation:
Calculate thickness of new shim:
- Add measurement A of output flange (previous) and measurement C of shim
(previous)
Then subtract measurement B (previous) from result A+C (previous)
- Subtract measurement B from measurement A of output flange (new)
- Then subtract result of step 2 from result of step 1.
READ NEXT:
IMPORTANT: Read and comply with notes on protection against
electrostatic damage (ESD
protection).
Replacement:
Before and after replacement, execute the "Repair" service function with
the BMW di
IMPORTANT: After completing work, check gear oil level, see
Replenishing /Changing
Transfer Case Oil (ATC 700) and top up if necessary.
Use only the approved gear oil in this transfer box.
NOTE:
SEE MORE:
Special tools required:
11 9 190
11 9 460
11 9 461
11 9 462
11 9 463
(cylinder bank 5 to 8)
Necessary preliminary tasks:
Read fault memory and make a documentary record.
Remove servomotor for left eccentric shaft.
Remove left cylinder head cover.
Remove all spark plugs on cylinder bank
Special tools required:
13 3 010
Necessary preliminary tasks:
Remove left underbody panelling.
Seal off water hoses at fuel pump with special tool 13 3 010
Fig. 54: Identifying Special Tool (13 3 010) On Water Hoses
Recycling
Fuel escapes when fuel lines are detached. Have a suitable collect